IMPROVEMENT OF AL-JAMARAT
BRIDGE & SURROUNDING AREA - MINA |
| |
|
Click on the image to view our portfolio |
| Client: |
Ministry of Municipal and Rural Affairs |
 |
| Main Contractor: |
Saudi Binladin Group |
| Consultant: |
Dar Al- Handasah |
| F.S.A Contract Value: |
280 Million SR |
| Completion: |
2009 |
| |
|
|
This four level segmental bridge with access ramps, service buildings and helipad towers is designed to carry the heavy flow of pilgrims during the holy period of Hajj. Each level of the bridge is composed of three ellipses and a passage extending over 600m with a variable span of 60m to 100m. In addition, each level of the bridge deck is composed of 1260 concrete precast segments that weigh between 44 and 60 tons. FSA scope of work includes the lifting and erection of precast segments using specially designed movable lifting devices, 70 tons capacity in addition to all prestressing, horizontal jacking, and geometry adjustment works. The technical parameters of the project and the deployed resources to achieve the works within the limited time make this project one of the most contemporary challenging constructions. |
| |
|
|
| |
|
| |
|
|
INTERSECTION OF SARY STREET AND PRINCE SULTAN STREET |
| |
|
Click on the image to view our portfolio |
| Client: |
Municipality of Jeddah |
| Consultant: |
Fluor Arabia |
| Contract Value: |
30 Million SR |
| Scope of Work: |
Turnkey |
| Completion Period: |
1 year |
| Completion: |
2009 |
|
 |
| |
|
|
Construction of a fly over at the intersection of Sary/Sultan Street. The bridge consists of post tension precast girders of 30m span each. |
| |
|
| |
|
|
| |
Mina Bulk Water Reservoir No. 2 |
| |
|
Click on the image to view our portfolio |
| |
| Client: |
Ministry of Municipal and Rural Affairs |
 |
| Consultant: |
Dar Al- Handasah |
| Contract Value: |
28 Million SR |
| Scope of Work: |
Turnkey Project |
| Completed |
1983 |
| |
|
|
Pioneering technology was needed to undertake this unique structural design of a reservoir with a capacity of 600,000 cubic meters of water.
The Aluminium roof cover measuring 45,000 m2 consists of two rows of inclined columns of 40m height with precast prestressed segmental beams spanning 150m located between each of the four columns, and suspended by prestressed cables from the top of the adjacent columns, to form the conical profile bearing the aluminium cover cladding. |
| |
|
|
|
| |
|
|
MAKKAH - MADINAH
EXPRESSWAY SECTION V |
| |
|
Click on the image to view our portfolio |
| Client: |
Ministry of Municipal and Rural Affairs |
 |
| Consultant: |
Nizar Kurdi |
| Contract Value: |
20 Million SR |
| Completed |
1984 |
| |
|
|
| This section extends over a length of 50Km and contains 24 bridges and interchanges most of them spanning deep in the valleys. The scope of work was the design of precast girders, procurement of moulds and technical know- how of introducing the precast segmental system plus the complete prestressing work and the erection of precast girders over the deep valleys for which the special technique of launching beams was introduced. |
| |
|
|
| |
|
|